Purpose |
Use Toggle Banding to add or remove banding. |
Prerequisites |
A stack set must exist. |
Steps |
To add banding: 1. In the Project List window, select a project. 2. Click Plans/Elevations.
3. Select at a Plan and Elevation. 4. Click Toggle Banding.
5. The Elevation displays with a line under the item that has added banding.
6. To remove the banding, click Toggle Banding and the line is removed. Edit Banding NoteTo add a note to a truss: 1. Right-click on a truss with a banding indicator.
2. Click Edit Banding Note.
3. Enter the Banding Note.
4. The banding indicator changes from a solid line to a dashed line when there is an associated banding note.
5. When hovering over a component with an associated banding note, the Banding Note displays in the tool tip.
When components with banding indicators are moved on the elevation Stacking List, banding indicators are removed . This also removes the Banding Note. For Best Practices, the stacking order should be finalized before the banding is applied. |
Related Topics |