Summary |
The Tasks tab displays all tasks associated with the project in a grid format for quick viewing and editing. Project tasks are initially populated based on default settings and can be modified for each project, or adjusted globally in the Administration Section. You can also use the Change Task Status to change task status. |
||||||||||||||||||||||||||||||
Window |
Project View - Tasks Tab
|
||||||||||||||||||||||||||||||
Field Descriptions |
The following table lists field descriptions.
|
||||||||||||||||||||||||||||||
Accessing |
1. In the Project List window, select a project. 2. In the Project View window, select Project Info. 3. Select Tasks Tab. With many plans and lots in a project, each with their own statuses, the Tasks tab may contain a lot of information. Grouping the information by column headers can help focus on critical information.
Rebuild Tasks from Defaults function To update tasks on existing projects to match new tasks and tracking level edits in the Admin > Task/Status tab:
Single Delivery Projects
|
||||||||||||||||||||||||||||||
Related topics |
Best Practices - Autofill fields |